Consent Items D1 - D9
Recommend approval of change order #1 to the construction contract with QUEST CIVIL CONSTRUCTORS TEXAS, LLC for the Govalle Tunnel Centralized Odor Control Phase I and II project in the amount of $282,770 plus additional contingency in the amount of $195,171.10, for a total contract amount not to exceed $4,576,534.20.
Recommend approval to execute change order #2 to the construction contract with MCLEAN CONSTRUCTION, INC., for Airport at Chesterfield Wastewater Improvements in an amount of $942,071.13 for a total contract amount not to exceed $7,120,709.13.
Recommend approval to negotiate and execute a two-year Interlocal Agreement with the University of Texas (UT) for consulting services regarding characterization of the influent to the City’s wastewater treatment plants for a total amount not to exceed $135,000.
Selection of ex-officio voting member for the Lake Travis Task Force
FY 2013 Proposed Budget
FY 2013 Proposed Budget
FY 2013 Proposed Budget
Vote on August 15, 2012 Budget Presentation Meeting for Budget Recommendation; if needed
Ratification of a 6-month requirement service contract with SENTRY SECURITY AND INVESTIGATIONS LP, (MBE), to provide unarmed security guard and patrol services at seven locations within the Austin Water Utility for a total estimated contract amount not to exceed $520,000.
Annual Update on the City of Austin and Lower Colorado River Authority Water Partnership
WTP4 Monthly Report
CALL TO ORDER – August 8, 2012, 6:00 p.m.
CITIZEN COMMUNICATION
APPROVAL OF MINUTES Approval of minutes from the June 13, 2012 Water & Wastewater Commission meeting.
Consent Items D1 - D9
Recommend approval of change order #1 to the construction contract with QUEST CIVIL CONSTRUCTORS TEXAS, LLC for the Govalle Tunnel Centralized Odor Control Phase I and II project in the amount of $282,770 plus additional contingency in the amount of $195,171.10, for a total contract amount not to exceed $4,576,534.20.
Recommend approval to execute change order #2 to the construction contract with MCLEAN CONSTRUCTION, INC., for Airport at Chesterfield Wastewater Improvements in an amount of $942,071.13 for a total contract amount not to exceed $7,120,709.13.
Recommend approval to negotiate and execute a two-year Interlocal Agreement with the University of Texas (UT) for consulting services regarding characterization of the influent to the City’s wastewater treatment plants for a total amount not to exceed $135,000.
Selection of ex-officio voting member for the Lake Travis Task Force
FY 2013 Proposed Budget
FY 2013 Proposed Budget
FY 2013 Proposed Budget
Vote on August 15, 2012 Budget Presentation Meeting for Budget Recommendation; if needed
Ratification of a 6-month requirement service contract with SENTRY SECURITY AND INVESTIGATIONS LP, (MBE), to provide unarmed security guard and patrol services at seven locations within the Austin Water Utility for a total estimated contract amount not to exceed $520,000.
Annual Update on the City of Austin and Lower Colorado River Authority Water Partnership
WTP4 Monthly Report